1 Year Warranty on Parts and Service
Official Distributor of Midwest Products

CTM Announcements


Click here to visit the CTM Air Conditioning Website

RECENT PROJECTS


B.P. TOWER REPAIR


AIR LIQUIDE


PETRO CANADA


McMASTER UNIVERSITY
2 CELL ADDITION


EATON'S CENTER SHOPPING MALL - TOWER REPLACEMENT


CONOCO PHILLIPS
TOWER COLLAPSE


CIBC BUILDING
TOWER REPLACEMENT


TORONTO STAR
NEW TOWER REPLACEMENET



STELCO NANTICOKE RPH TOWER, NOW US STEEL


STELCO NANTICOKE NEW
2 CELL MARLEY TOWER



STELCO NANTICOKE NEW ECODYNE TOWER


SUNCOR ETHANOL PLANT
NEW TOWER


VALE INCO ORFORD STACK


XSTRATA FALCONBRIDGE SUDBURY - TOWER REBUILD


VALE INCO LTD.
ACID PLANT TOWER


VALE INCO LTD.
TOWER REBUILD


ALGOMA STEEL INC.
TOWER REBUILD


AYLMER ETHANOL PLANT
NEW FIBERGLASS TOWER

 

 

B.P. - TOWER REPAIR



PROJECT DETAILS

The three cell tower was originally designed as a wet/dry cooling tower, with mechanically operated internal dampers to reduce the plume.

Each cell was fitted with a 12’ wide x 30’ high finned coil on one side of the tower and the opposite side of the tower consisted of Vee bar with 16’ air travel.

The return water from the process was pumped through the finned coil and then through the cross over pipe and into the hot water basin.

With plume abatement no longer an issue the system was redesigned by Colt Engineering to cool 13,500 USGPM from 95 to 80 @ 73 wet bulb, and the project consisted of the following modifications;

  • All the finned coils were completely removed
  • New 20’ diameter FRP fans were installed for maximum airflow
  • New hot water basins and nozzles to match water flow
  • New FRP louvers
  • New hangers and Vee bar
  • Structural repairs

PROJECT TESTIMONIALS

Click here to visit the CTM Air Conditioning Website

"Thank you for doing an excellent job... we have met our desired performance as indicated by our follow-up field testing."

- William J. Kay, Engineering Supervisor
  BP Canada Energy Company

Click here to read a letter of reference
from our client.

Back To Top    



AIR LIQUIDE







PROJECT DETAILS

Erection of two cell Midwest Induced Draft Counter flow, each cell 30’ x 30’

Back To Top    



PETRO CANADA















PROJECT DETAILS

This project consisted of major structural repairs to the three cell Fluor Induced Draft Counter Flow Tower and the two cell Single Flow Marley Cross Flow Tower.

Back To Top    



McMASTER UNIVERSITY - 2 CELL ADDITION












PROJECT DETAILS

The customer required an additional cooling tower be added to the following design conditions:

Flow: 3,395 usgpm
Entering Water: 95.0°F
Leaving Water: 85.0°F
Wet Bulb: 76.0°F

Site Conditions:
Install new packaged steel or build additional cells onto the existing cross flow induced draft wood tower.

The last photograph is standing on the existing fan deck of the original tower looking at the new two cell addition. We had reconstructed the original tower and added the new fibreglass fan stacks in previous years. Note: New Hot water basin joins to original hot water basin forming one complete tower.

The third photograph shows the existing tower and in the background with the new safety railing are the new CTM cells that were added to the existing.

Back To Top    



EATON'S CENTER SHOPPING MALL - TOWER REPLACEMENT









PROJECT DETAILS

Original Equipment: 2 cell Marley Series 15; installed 1975; Designed HH Angus
Design Conditions: 6,600 usgpm
Entering Water: 95ºF
Leaving Water:  85ºF
Wet Bulb: 76ºF

Site Conditions:
Because the system is heat recovery, the cooling tower operates all year long therefore we were required to rebuild the system while the chilled water plant continued to operate throughout the winter months.

The towers are located on the roof 35 stories above grade at the corner of Yonge and Dundas Street. Crane lifts were unreasonable given the site conditions and the height.

Photographs are of the first phase of the project. The first shot shows the January 2004 completion of a section of the tower while the dilapidated original section continues to operate. The second shot is of the fibreglass casing and access door that replaced the original MNA asbestos casing. Note the new fibreglass fan stacks protruding from the top of the tower.

Back To Top    



CONOCO PHILLIPS - TOWER COLLAPSE









PROJECT DETAILS

The 63,000 USGPM, 9 cell single flow cross flow tower located in Burstal about 120 KM north of Medicine Hat in Alberta was struck by a tornado in July of 2005 which resulted in the total collapse of all 9 cells and the entire plant had to be shut down.

We visited the job site and with in days of the collapse we were part of the team involved in supplying and setting up over 30 portable rental cooling towers which were piped into the existing sump, allowing the plant to be in operation within 6 weeks of the collapse.

The rental towers were in operation for approximately 2 months while a new cooling tower was erected within the original concrete basin.

Back To Top    



CIBC BUILDING – TOWER REPLACEMENT















PROJECT DETAILS

Original Equipment: 2 x 3 cell Marley Series 10; Installed 1970; Designed ECE Group
Design Conditions: 4,150 usgpm
Entering Water: 105/95ºF
Leaving Water:  85ºF
Wet Bulb: 76ºF

Site Conditions:
Because the system is heat recovery, one bank of cooling towers operate all year long therefore we were required to rebuild the system while the chilled water plant continued to operate throughout the winter months.

The towers are located on the roof 56 stories above grade at the corner of Bay and King Street. Crane lifts were unreasonable given the site conditions and the height.

Back To Top    



TORONTO STAR BUILDING - NEW TOWER REPLACEMENT















PROJECT DETAILS

The existing three cell Series 10 Marley Cooling Tower was in poor condition and had to be replaced without interruption to the operation of the plant,

This was achieved by keeping two cells in operation at all times while each cell was completely removed and replaced.

In addition to the tower replacement, the concrete piers were repaired and new hot dipped galvanized supporting steel was replaced at the same time.

The new three cell Midwest Cross Flow Tower was designed to cool 4000 USGPM from 100 to 85 @ 76 wet bulb temperature.

Back To Top    



STELCO NANTICOKE RPH TOWER, NOW US STEEL














PROJECT DETAILS

The hot water basin supports on one cell of this four cell cooling tower had collapsed resulting in major bypass of water over the louver face of the tower and damage to louvers, hanger grids and Vee bar.

The remedial work consisted of the following;

  • New hot water basins and supports
  • New fan deck
  • Major structural repairs
  • Repairs to louvers
  • New hangers and Vee bar

Back To Top    



STELCO NANTICOKE - NEW 2 CELL MARLEY TOWER, NOW US STEEL










PROJECT DETAILS

The project required the simultaneous erection of a two cell Marley Series 600 Cross Flow Cooling Tower and a single cell Ecodyne Cross Flow Cooling Tower.

Work was completed within a very aggressive schedule, with zero injuries or lost time.

PROJECT TESTIMONIALS

Click here to visit the CTM Air Conditioning Website

"Thank you to CTM for the excellent work that you did... CTM had excellent supervision and tradesmen to do the work. Your adherence to the AKS safety policies and routines were faultless."

Rob Girvan, General Construction Superintendent
Aker Kvaerner Songer

Click here to read a letter of reference
from our client.

Back To Top    



STELCO NANTICOKE - NEW ECODYNE TOWER, NOW US STEEL













PROJECT DETAILS

The project required the simultaneous erection of a two cell Marley Series 600 Cross Flow Cooling Tower and a single cell Ecodyne Cross Flow Cooling Tower.

Work was completed within a very aggressive schedule, with zero injuries or lost time.

PROJECT TESTIMONIALS

Click here to visit the CTM Air Conditioning Website

"Thank you to CTM for the excellent work that you did... CTM had excellent supervision and tradesmen to do the work. Your adherence to the AKS safety policies and routines were faultless."

Rob Girvan, General Construction Superintendent
Aker Kvaerner Songer

Click here to read a letter of reference
from our client.

Back To Top    



SUNCOR ETHANOL PLANT - NEW TOWER















PROJECT DETAILS

Design: 4 cell Midwest Tower Induced Draft Counterflow
Design Conditions: 27,000 usgpm
Entering Water: 94ºF
Leaving Water: 84ºF
Wet Bulb: 76.5ºF

Site Conditions: A new Ethanol plant in Ontario built at grade on a concrete basin.

PROJECT TESTIMONIALS

Click here to visit the CTM Air Conditioning Website

"The exceptional performance of your workers, in both quality and safety, was noted and appreciated. Your workers managed to achieve commendable safety results."

- Michael O'Connor, Project EHS&S Manager
  Suncor Energy

Click here to read a letter of reference
from our client.

Back To Top    



ORFORD STACK















PROJECT DETAILS

This is a one of a kind natural draft cooling tower which was built in 1974 and is located at INCO in Sudbury.

The scope of work involved the complete removal of the entire asbestos cement casing panels, drift eliminators, heat transfer surface and spray system.

These asbestos components were replaced with fiberglass casing, high efficiency PVC eliminators, high efficiency cross fluted PVC heat transfer media and Schedule 40 PVC spray system and nozzles.

In addition to this there was significant degradation and spalding of the concrete sump and supporting concrete columns and beams.

The columns were cleaned up and fitted with Stainless forms and filled with high strength fast drying specialty grout, all concrete beams were replaced with Steel beams and the concrete inlet louvers were replaced using marine grade pressure treated plywood complete with a steel guard rail.

The bulk of the work as done during the summer shutdown in 2005 & 2006, however much of the upper level columns were done over the winter with the tower online in conditions well below -20 Celsius.

PROJECT TESTIMONIALS

Click here to read the Orford reference letter

"Your company attained an outstanding safety record of zero injuries over the entire construction period. We look forward to working with you in the near future in the hope of achieving similar safety results. "

Jim Amson, P. Eng.
Engineering Maintenance Services Group

Click here to read a letter of reference
from our client.

Back To Top    



XSTRATA FALCONBRIDGE SUDBURY - TOWER REBUILD

















PROJECT DETAILS

  • 11 day shutdown
  • 30 men on the job
  • 2007 Shutdown
  • Replaced fill media in two cells
  • Structural repairs to all cells

Back To Top    

VALE INCO LTD. ACID PLANT - TOWER















PROJECT DETAILS

This project involved structural repairs during the 2006 summer shutdown.

PROJECT TESTIMONIALS

Click here to visit the CTM Air Conditioning Website

"We were very impressed by the professionalism that your team displayed. The work performance was of the utmost quality."

- I.A. Chaumont, Superintendent
  Chris Doyle, Plant Manager
  Copper Cliff Smelter Complex
  Engineering Maintenance Services Group

Click here to read a letter of reference
from our client.

Back To Top    



VALE INCO LIMITED - COOLING TOWER REBUILD









PROJECT DETAILS

Rebuild of # 3 Oxygen Plant 3 Cell Wood Counter flow Cooling Tower.
Removed and replaced approximately 80% of all structural members, installed all new drift eliminators and replaced some damaged sections of casing panels.

Site Conditions:
All work completed on schedule with no injuries during 10 day September 2007 Plant Shutdown to the customers’ satisfaction.

Back To Top    



ALGOMA STEEL INC. - COOLING TOWER REBUILD









PROJECT DETAILS

Rebuild of # 7 Blast Furnace 4 Cell Series 15 Wood Cross Flow Cooling Tower.
Existing wooden fan stacks replaced with new fiberglass stacks 14’ diameter and 13’ 6” high connected to the existing 50’ high steel stacks.

Existing steel fan assemblies replaced with new high efficiency fiberglass fans and laser aligned and rusted out sprinkler system replaced in places with new.
All louver columns and louvers replaced.

New fan deck, hot water basins installed along with some internal structural repairs and new internal walkways complete with safety rails

Site Conditions:
All work completed on schedule with no injuries during 21 day July 2007 Plant Shutdown to the customers’ satisfaction.

Back To Top    



AYLMER ETHANOL PLANT - NEW FIBERGLASS COOLING TOWER











PROJECT DETAILS

Design: 3 cell Midwest Tower Induced Draft Counterflow
           100% Fiberglass Construction
Design Conditions: 21,000 usgpm
Entering Water: 94º F
Leaving Water: 84º F
Wet Bulb: 77º F

Site Conditions:
This new Ethanol plant built by North America Construction Ltd in Aylmer Ontario. The 3 cell FRP Fiberglass tower designed by Midwest Towers and erected by CTM from October 2007 to December 2007, overall project completion date is August 2008.

PROJECT TESTIMONIALS

Click here to visit the CTM Air Conditioning Website

"CTM’s experience in cooling tower construction was apparent in the manner in which the project was approached.  Not only was the work performed in an expeditious, cost effective manner, but also to a high standard of safety and professionalism.  I fully commend both your management and labourforce."

- Perry McPherson, Project Manager
  North America Construction (1993) Ltd.

Click here to read a letter of reference
from our client.

Back To Top    



 

 

 

HOME PRODUCTS PARTS SERVICE PROJECTS RENTALS CONTACT


 
 
 



         © 2007 CTM Inc. All Rights Reserved



Element Design International