Project Description
100 Wynford Drive – Bell Canada
Toronto – Ontario
Problem:
– 2 cell forced draft counter flow unit had numerous issues and had to be addressed before the winter operation season.
Solution:
– Removed all fill, eliminators, mechanicals and fan snouts.
– Sandblasted the tower interior and sealed.
– Installed new fill media, eliminators, fan snouts and mechanicals.
Project Details
CLIENT
Bell Canada
PROJECT TYPE
Commercial
Time Frame
12 weeks