Problem:
– 2 cell forced draft counter flow unit had numerous issues and had to be addressed before the winter operation season.

Solution:

– Removed all fill, eliminators, mechanicals and fan snouts.
– Sandblasted the tower interior and sealed.
– Installed new fill media, eliminators, fan snouts and mechanicals.

Project Details

CLIENT

Bell Canada

PROJECT TYPE

Commercial

Time Frame

12 weeks