750 Lawrence – CIBC Data Centre

North York, Ontario

Problem:
– Existing 3 cell Series 10 wood cross flow had fallen into a state of disrepair. The tower ran 24/7 so we had to replace the tower and still have at least
one cell running.

Solution:
– Isolated the towers to allow repairs to take place. Brought material up through the building.
– Removed and replace two cells during stage 1 of project. Once rebuilt cells were complete the tower was switched over to allow the replacement of the remaining single cell unit.

Project Details

CLIENT

CIBC

PROJECT TYPE

Commercial

Time Frame

12 weeks (Nov – Feb)

Project Gallery

Bottom of tower with rusting pipe
old cooling tower cold water basin with float prior to repair
Running crossflow tower with newly installed fill, water running down fill and mist in the air
Crossflow tower newly replaced wood louvers
Crossflow tower newly rebuilt interior plenum
Crossflow tower newly rebuilt wood louvers
Rooftop view of newly replaced fans with motors
side view of older crossflow tower rusting side panel