Problem:
– BAC FXT 200
– Previous installer (not CTM) did not install fill correctly and tower was spilling water out all over. Would not maintain required tower temps for chiller.

Solution:
– Replace fill pack and metal supports. Install plates behind fans to eliminate direct pressure on fill.
– Tower now operates efficiently, with water loss down to acceptable evaporation.

Project Details

CLIENT

South Center Executive Tower

PROJECT TYPE

Commercial

Time Frame

2 days

Project Gallery

CTM technicians installing fill into a cross flow tower
CTM technicians installing fill into a cross flow tower
CTM technicians installing fill into a cross flow tower
CTM technicians installing fill into a cross flow tower
CTM technicians installing fill into a cross flow tower
CTM technicians installing fill into a cross flow tower
new fill installed in the cross flow cooling tower
CTM technicians installing fill into a cross flow tower